Oracle – Block C

Oracle Phase 2 – Block C – Base Build & Fit Out

 

A 54,000 sq. ft design and build contract to deliver new office space. This block had a live Data Centre serving the campus that had to be maintained at positive pressure with strict security, dust and vibration controls throughout the project lifecycle. Full envelope refurbishment with new curtain walling, limestone cladding and entrance. New retail café, rotating climbing wall and interactive classroom complete with full audio-visual capabilities.

Project Works:

  • A full plant strip out.
  • Atrium infills.
  • Installation of new air handling units.
  • CAT A & B installation including new Starbucks café fit out.
  • A rotating climbing wall.
  • Interactive classroom complete with full audio-visual capabilities.

Oracle multiple projects:

mac has been contracted by Oracle to renovate and upgrade multiple blocks in the Eastpoint campus for the company’s growing employee base in Dublin. Works have included structural enhancements, façade replacements, plant strip out and full mechanical & electrical installations. New restaurant, gym and exercise facilities with state of the art audio visual and meeting space. Smart buildings with intelligent BMS with two buildings achieving LEED Platinum accreditations.

Oracle EastPoint Business Park, Dublin – Read about Phase 1 Block B and Phase 3 Block A.

 

Total Duration of the 3 phases: 92 Weeks

Key Project Challenges:

  • Live business park
  • Structural alterations
  • Live Data Centre
  • Live integrated services

Project Details

Size: 54,000 sq. ft.
Duration: 28 Weeks
Team: Design and Build - mac
Meehan Associates
Hardy Partnership
Horgan Lynch
QA Designs
TOTP
PMEP
JVT