The project involved modifications and additions to the existing MEP services to the client’s ‘Ohana’ global specification. The installation included relocation of existing FCU’s and associated services and the installation of new FCU’s, cross talk attenuators, fire dampers and cavity barriers to suit the new design layout.
The project was also successfully delivered early and within budget to the client’s satisfaction.
You appreciated the whole of the project was subject to a tight completion schedule and you did more than your part to ensure the target date was achieved without compromising the quality standards we required – Erika Woodcock, Salesforce.com
This project was completed by our Dublin Team. #TEAMmac
Size: | 25,000 sq ft |
Duration: | 11 weeks |
Team: | JLL MCA Architects Homan O'Brien |