Strip back to shell and CAT A refurbishment of a nine-floor building in the heart of Westminster. Works also included the removal and replacement of existing M&E services with a fully exposed services installation. Structural alterations included a new lift shaft, staircase and slab infills along with roof and balcony decking areas.
Project Works Description
Mechanical Scope
Replacement of existing chilled water and LTHW systems, Fan Coil Units, ductwork, water systems, drainage and ancillary systems, leak detection system, alterations and modifications to existing sprinkler pipework and installation of a new Building Management System.
Replacement of existing lighting and small power distribution, emergency lighting, fire alarm, access control and HV upgrade.
Further Information:
Size: | 68,000 sq. ft. |
Duration: | 42 weeks |
Team: | Core Five Core Five Ben Adams Architects Max Fordham Heyne Tillet Steel |