The first building fit out is complete at Optum with two more to go. It was a challenging programme working with many new subcontractors and suppliers in a new location.
This project was completed by our Dublin Team. #TEAMmac
The mac team completed another successful delivery with the Handover of Building 3 for Optum, Letterkenny. The local Optum / UHG team today passed on their praise to the team for the high quality and standard of the new addition to the Campus. The mac team that I have been working with onsite have been an absolute pleasure to work with from the offset. Their professional + diligent approach to any issues large or small to address is clearly evident – Louise Dwyer, Project Manager, Project & Development Services JLL
Size: | 84,000 sq. ft. |
Duration: | 57 weeks |
Team: | JLL RKD METEC |