Mountpark Logistics Unit B

Mountpark Logistics, Baldonnell Business Park, Dublin.

The project was a JCT 2005 Design and Build of a full fitted out logistics warehouse with 9000 sq. ft. office and welfare area over two floors.

The building comprised of steel frame double portal frame founded on pad foundations. The site areas involved a full ground solution offered by mac-group for lime & cement stabilisation achieving a CBR of 15%. The earthworks and ground improvement works were circa 23000m3 of material being reengineered to achieve building and external works plateau areas from site won materials from onsite borrow pits.

External landscaping involved a site area of circa 8 acres for the provision of new public open space and walkways including the provision of green gym equipment. The project also involved the construction of 2 bridges over the River Camac. One bridge was a piled abutment bridge with precast bridge beams. The second bridge was formed using a precast concrete culvert structure and required a river diversion for the realignment of the river. Inland Fisheries were also engaged with for the planning of the bridge works and also the relocation of fish from the diverted river to the new aligned river.

The Building was fully fitted out with High Bay Racking providing space for 32000 pallets and a full Roof Mounted Sprinkler installation and associated water tanks and pump house. A Foul Pumping Station was also installed as part of the works

Project Works include:

  • Kingspan composite wall and roof cladding.
  • AOV’s to warehouse roof.
  • Siphonic drainage system.
  • Metal deck & concrete office 1st & 2nd floor slabs.
  • 30,000 sq. ft. warehouse mezzanine.
  • FM2 laser warehouse floor slab.
  • 22 Dock Levellers and shelters including 4 Euro docks.
  • Concrete service yard.
  • Permeable asphalt carpark area for 150 cars.
  • Electrical vehicle charging for 6 vehicles.
  • Asphalt access roads and grasscrete fire tender route.
  • Full Mechanical installation to Office and Welfare areas including Thermal dynamic Air to heat pumps and full VRF heating and ventilation system and Fire Hose Reel Installation to the warehouse.
  • Full Electrical installation to Office and Welfare areas including the construction of a new ESB substation serving the Building. Full Security and CCTV to the entire building both internally and externally.

Key Challenges:

  • Working adjacent to the Casement Aerodrome.
  • Archaeological discoveries during earthworks
  • Managing on site Japanese Knotweed
  • Working adjacent to the River Camac (engagement with Inland Fisheries).
  • Inclement Weather conditions during construction.

Unit B was awarded a Gold Considerate Constructors Scheme 2020 National Site Award.

Read more about this award on our blog here.

Read about Phase 1 Unit A here.

After the success of Phase 1 mac were awarded the fit out of Unit A by the new client moving into the building read more on this fit out here.

Read more about Mountpark Logistics here.

Share

Project Details

Value:€13,700,000
Size:207,500 sq.ft.
Duration:44 Weeks
Team:Client: Mountpark Logistics
Architect: JSA Architects
Civil Engineer: Punch Consulting Engineer
Steel Frame Consultant: Complete Design Partnership (UK)
M&E Consultant: OBMG
PM/PQS: Projex Building Solutions (UK)

Do you have a project you'd like to talk to us about?