As part of Mastercard’s new technology campus at South County Business Park mac-group were appointed under a JCT Design & Build 2016 Contract for the CAT B Fit Out of the new Grade A office building at One South County. This project has achieved LEED Platinum rating & is on target for a WELL Platinum rating

Architectural Scope:

Design and installation of specialist joinery, partitions and glazed partitions systems, ceilings, floor finishes, decorations, wayfinding and bleacher seating to provide:

  • Staff café
  • Townhall area
  • Reception
  • Customer experience centre
  • Open plan offices, meeting rooms and collaboration areas
  • Interview rooms
  • Learning labs
  • Board Room
  • Training rooms
  • Parenting rooms
  • Games Rooms
  • Multi-purpose rooms

Project Works include:

  • High-end CAT B fit out inclusive of feature lighting and suspended ceilings, along with a mix of various floor finishes and wall panelling types within the office areas.
  • Significant specialist joinery elements integrated to the 4th floor café and ground floor dining and general purpose spaces.
  • Upgrade of existing chilled water AC and ventilation system, along with new bespoke ventilation systems to the 4th floor and ground floor kitchen/dining areas. Purpose specific stand-alone AC systems installed within all IDF & MDF Rooms.
  • Fit out of new lighting, general power and protective services including the integration of a new generator. Complete roll-out of new fully installed and commissioned IT, security & AV systems.
  • This is a Mastercard innovation hub and presents extremely high spec architectural finishes and state-of-the-art technology
  • Design and construction of the bespoke ‘Customer Experience Centre’ incorporating large AV walls, folding partition systems and specialist joinery
  • Design and construction of a new specialist security unit within the building undercroft
  • Population of beehives at roof level

Mechanical Scope:

  • Modification and installation of existing and new heating, ventilation and air conditioning services to service offices, meeting rooms, café, atriums etc
  • Installation of mechanical services to SER/ MER Rooms with associated CRAC units, gas suppression & VESDA systems
  • Installation of new and modification to existing FCUs
  • Installation of acoustic attenuation throughout
  • Transfer fans and CO2 controls
  • LTHW & chilled water pipework
  • Extract systems
  • Drainage
  • Fire suppression systems
  • Leak detection

Electrical Scope:

  • Alterations and modifications to existing systems
  • General, feature and emergency lighting installations an controls
  • General LV Power
  • UPS Installation
  • IT Structured Cabling
  • Security & Access Control Systems
  • Audio Visual
  • Fire Detection and alarm
  • LV Switchgear and Distribution Boards
  • Back up generator

Key Challenges:

  • The delivery of a highly complex and large fit out during the COVID-19 pandemic

Project works completed by our team in Dublin #TEAMmac

Mastercard is a global pioneer in payment innovation and technology connecting billions of consumers, consumers, issuers, merchants, governments, and businesses.

Project Details

Value: €21m
Size: 107,000 sq. ft.
Duration: 50 weeks (exc. COVID shutdown)
Team: Project Manager: Cushman & Wakefield
Quantity Surveyor: Fanshawe
Architect: Interior: Architects
Services Consultant: Axiseng