Houghton Mifflin Harcourt Refurbishment
CAT B refurbishment across 2 floors in Trinity Plaza. The objective was to reconfigure the existing office space to increase desk numbers with new finishes and new specialist joinery installations including new tea stations. This project was completed over 3 phases while the client remained in the building.
This project was completed by our Dublin team #TEAMmac
Read more about Houghton Mifflin Harcourt here
Size: | 30,000 sq ft |
Duration: | 12 weeks |
Team: | Turner & Townsend RKD Baker O'Reilly |