Project Overview

Installation and upgrade of new ESB Switch Station

Project Works

  • Chiller plant room
  • LV board
  • Trench heaters & ducting in a limited 200mm floor void/plenum space
  • Dry air coolers and new rooftop plant room

Works have been carried out over 11 phases with swing space created on each floor.  – 75 St. Stephen’s Green

This project was completed by our Dublin Team. #TEAMmac

When we got our tender documents back from the 5 big brand contractors in Dublin and we assessed them all, mac stood out because they clearly understood our concerns – Michael Hynes, Director, Head of Real Estate, Hudson Advisors Ireland Ltd.

 

Project Details

Size: 120,000 sq. ft.
Duration: 55 weeks
Team: Hudson Advisors
Linesight
OBFA Architects
Arup